WtE boiler products of Vietnam entered the Japanese market

(VLR) Before manufacturing the Waste to Energy (WtE) boiler for this project, Doosan Vina has conducted five tests for Japanese customer to evaluate. That shows the extremely strict quality requirements of the Japanese market.

The boiler pressure components using the WtE technology are being loaded onto the ship at Doosan Vina's dedicated port in Dung Quat EZ for export to Japan (Photo: Doosan Vina)

The boiler pressure components using the WtE technology are being loaded onto the ship at Doosan Vina's dedicated port in Dung Quat EZ for export to Japan (Photo: Doosan Vina)

The Fushimi Kankyo Hozen project was signed between Doosan Vina and Mitsubishi Heavy Industries Environmental & Chemical Engineering Co., Ltd, Japan on September 4, 2019 to supply 228 tons of boiler pressure equipment and welding nickel alloy which are used in a WtE power plant in Fushimi, Kyoto, Japan.

After more than nine months of production, today (May 13, 2021), Doosan Vina successfully shipped the first shipment weighing 189 tons of boiler pressure components using the WtE technology to a power plant at Fushimi, Kyoto, Japan. This is a good signal for Doosan Vina’s a production and business in particular and Quang Ngai in general when the national economy is facing the difficulties of the increasingly complicated COVID-19 epidemic wave.

In this first shipment, Doosan Vina shipped a total of 58 packages weighing 189 tons including Coil, Panel, Header, and Link. After the installation is completed, they will help burning garbage and converting thermal energy into electricity.

The completion of this shipment has contributed to bringing the company's total export turnover from the beginning of the year to 10,000 tons (Photo: Doosan Vina)

The completion of this shipment has contributed to bringing the company's total export turnover from the beginning of the year to 10,000 tons (Photo: Doosan Vina)

Sharing about the project, Park Jae Bong, Director of the Boiler shop said “We encountered many difficulties during fabrication, assembly, and inspection for this project because of the customer’s high requirements and this is the first time Doosan Vina produced the WtE technology boiler. However, with the unceasing efforts and creativity as well as strict compliance with all production processes, we have successfully produced the order.”

Before implementing this project in August 2020, we did five Mock-up tests for the customer to evaluate and we passed. That shows our customer’s extremely strictly demands for this WtE products, Mr. Park added.

Currently, Vietnam and the world are facing the complicated COVID-19 epidemic but Doosan Vina always well performs the "dual goals" of both preventing and combating the COVID-19 epidemic while maintaining the production activities to create a stable income for nearly 2,600 employees of the company and subcontractors. Up to now, the project is up the schedule and reached 97%. The rest volume of the project is planned to be completed and handed over to the customer on May 31, 2021.

Besides the Fushimi Kankyo Hozen project, Doosan Vina is also urgently manufacturing other projects for domestic and oversea such as Heurtey Heater Radiant Section, Jawa # 9 & 10, Van Phong 1, Song Hau 1, Palu 3, Gemalink and more. The completion of this shipment has contributed to bringing the company's total export turnover from the beginning of the year to 10,000 tons.

Thụy Hậu

Ý kiến bạn đọc

Chưa có ý kiến nào. Hãy là người để lại ý kiến đầu tiên.

Ý kiến của bạn

0

Tối thiểu 10 chữTiếng Việt có dấuKhông chứa liên kếtGửi bình luận

Vui lòng nhập mã bảo mật để gửi bình luận lên hệ thống
Gửi bình luận

Chuỗi cung ứng logistics 2021: Thách thức mới cũ liên tục xuất hiện

7 Giờ trước

Năm 2020 đi qua, chúng ta có thể phần nào cảm thấy nhẹ nhõm hơn khi vô số thách thức do COVID-19 gây ra cho tất cả mọi người từ doanh nghiệp, trường học và cộng đồng đã tạm thời lắng xuống. Dù vậy, năm 2021 cũng không dễ dàng để mọi thứ về lại bình thường như trước. Nhiều thách thức liên quan đến đại dịch vẫn tồn tại, vẫn còn nhiều khó khăn ẩn giấu hơn - đó chính là các yếu tố của chuỗi cung ứng.

Cao tốc Cam Lâm - Vĩnh Hảo: Vì sao chưa ký hợp đồng PPP?

10 Giờ trước

Liên danh nhà đầu tư trúng thầu tuyến cao tốc Cam Lâm - Vĩnh Hảo cho biết kế hoạch triển khai dự án đề ra trước đó đã đổ bể. “Việc đàm phán hợp đồng với Bộ GTVT bế tắc kéo dài, không biết đến bao giờ mới đủ cơ sở triển khai”, đại diện Liên danh cho biết. Hệ quả của việc chậm trễ này vừa gây thiệt hại cho doanh nghiệp vừa khiến thời gian hoàn thành tổng thể toàn dự án cao tốc Bắc - Nam chậm lại.

Diễn Châu - Bãi Vọt: Tuyến huyết mạch, trục xương sống trên cao tốc Bắc - Nam

12 Giờ trước

Việc đầu tư xây dựng tuyến đường bộ cao tốc Bắc - Nam đoạn Diễn Châu - Bãi Vọt có vai trò hết sức quan trọng, thiết yếu đối với sự phát triển kinh tế - xã hội, đảm bảo quốc phòng - an ninh của cả nước nói chung và 2 tỉnh Nghệ An, Hà Tĩnh nói riêng.

Thời tiết

Hiện tại

°

Nguồn: Weathers Underground

Tỷ giá ngoại tệ

Tỷ giá ngoại tệ cập nhật vào 25/06/2021 20:45
Mã NTTiền mặtChuyển khoảnBán
AUD17,027.6817,199.6817,738.94
EUR26,636.9426,906.0028,028.55
GBP31,182.2731,497.2532,484.78
JPY201.51203.55212.04
SGD16,731.4316,900.4317,430.31
THB640.04711.15737.86
USD22,880.0022,910.0023,110.00
Nguồn: Vietcombank

Giá xăng dầu

Giá xăng, dầu cập nhật ngày 25/06/2021 11:45
Loại xăng dầuĐơn vịGiá vùng 1Giá vùng 2
Dầu hỏaVND/L1441014690
DO 0,001S-VVND/L1579016100
DO 0,05SVND/L1544015740
Xăng E5 RON 92-IIVND/L1904019420
Xăng RON 95-II,IIIVND/L2016020560
Xăng RON 95-IVVND/L2026020660
Nguồn: Petrolimex