Let's put Hai Van tunnel 2 into operation

(VLR) Hai Van Tunnel 2 - a part of the Tunnel project through the Deo Ca Pass was already completed. However, the time for the Tunnel 2 going through Hai Van Quan and connecting Hue - Danang cities to officially join the North - South national route has not been confirmed yet.

THE INVESTOR COMPLETED THE PROJECT AHEAD OF SCHEDULE

During the implementation and construction of Hai Van Tunnel 2, the investor faced many difficulties related to technical requirements when they must drill the tunnel 2 but also maintain the operation process along with ensure the security for the test of Hai Van Tunnel 1 (time to close the tunnel gate for blasting, controlling the vibration and monitoring the deformation of the Hai van Tunnel 1); as well as meet the strict requirements of environment protection when the construction locates in the territory of 2 local regions owning two key economic sectors including tourism and alquaculture.

In addition, from early 2020, the COVID-19 epidemic had severely impacted on the completion timeline of all construction categories when the building was delayed temporarily and applied the social distancing following the direction of the Government and local authorities. However, by putting an effort and spirit of challenge overcoming, the investor and related parties already completed the construction with the good quality accordance with the design documents and current technical standards. All construction work finished on 30th Sept 2020, that is 3 months ahead of the schedule approved by the Ministry of Transport.

The completion milestone was officially recorded on 20th Nov 2020 when the National Evaluation Committee had inspected the Hai Van Tunnel and approved the acceptance result of the Ministry of Transport, marking the completion of the Hai Van Tunnel 2.

“We mobilized thounsands of billion VND for this investment and completed the construction following the contract articles, however, to date, the bank is restructuring the debt hence the group must focus on paying the current debt by ourselves and have no money for the tunnel operation”, said Mr Thang. “If the governmental authorities commit to implement the disbursement of the capital, the group will keep working with the bank and put the Hai Van Tunnel 2 in use”

The evaluation meeting was chaired by Deputy Minister of the Ministry of Transport, currently as Vice Chairman of the State Council for Acceptance result of the construction works, Le Quang Hung. In his conclusion speech, Mr Le Quang Hung already praised the hardworking of the investor, implementation agencies, monitoring agencies and the government authoritized agencies to finish the project ahead of the schedule. Through the review and evaluation opinions, the State Evaluation Council all agreed with the final report which is that the Hai Van Tunnel 2 already fulfilled the requirements to be ready for the vehicle circulation and continue several steps for the complete test.

Speaking at the meeting, Mr Le Dinh Tho – Deputy Minister of the Ministry of Transport, representing for State management agency, has highly evaluated the capacity of Deo Ca group at the project investor role: “Deo ca is one of the leading group in implementing the transport constructions. With many famous projects, Deo Ca has a wealth of experience, especially in construction organization, quality control, progress control, environment protection and other issues related to safety and security”

Talking about the meaning in pushing the social – economic development brought by the Hai Van Tunnel 2, Mr Nguyen Van Phuong, Vice President of the Thua Thien – Hue People’ Committee, expressed his desire to put the construction into operation soon in order to enhance the connection between two big cities of the Middle, including Thua Thien- Hue and Da Nang, and expand trade between the North and the South, grow the social-economic development for the key economic regions in the Middle and all over the country.

A LACK OF BUDGET FOR OPERATION

At this moment, the investor has still not defined exactly the time to put the tunnel into operation, due to several objective reasons. Mr Phan Van Thang, Vice President of Deo Ca Group and representative of the investor, acknowledged that the operation cost of the Hai Van Tunnel 2 might be about 150 billion VND per year, while the project cost jumped over the line due to a lack of 1,180 billion VND of the state capital that was commited by the Government. In addition, the amendment on toll fee rules at La Son – Tuy Loan station for reimbursement of the project on the signed contract was still not approved by the authoritized agencies.

“We mobilized thounsands of billion VND for this investment and completed the construction following the contract articles, however, to date, the bank is restructuring the debt hence the group must focus on paying the current debt by ourselves and have no money for the tunnel operation”, said Mr Thang. “If the governmental authorities commit to implement the disbursement of the capital, the group will keep working with the bank and put the Hai Van Tunnel 2 in use”.

It has been known that the Ministry of Transport has reported to the Government about the obstacles in the financial option of the project Hai Van Tunnel 2; in particular, the Ministry recommended that the Government should prepare the 1,180 billion VND of the State budget soon in the mid-term investment plan from 2021 – 2025 to support the project according to the articles and commitments in the contract.

Ngoc Trang

Ý kiến bạn đọc

Chưa có ý kiến nào. Hãy là người để lại ý kiến đầu tiên.

Ý kiến của bạn

0

Tối thiểu 10 chữTiếng Việt có dấuKhông chứa liên kếtGửi bình luận

Vui lòng nhập mã bảo mật để gửi bình luận lên hệ thống
Gửi bình luận

Việt Nam có thêm 8 bến cảng mới

Ngày 15/04/2021 lúc 09:31

Bộ GTVT vừa có quyết định công bố danh mục bến cảng thuộc các cảng biển Việt Nam.

Nghệ An 'rót' gần 1.100 tỷ đồng cho 21 dự án giao thông

Ngày 16/04/2021 lúc 14:51

Trong năm 2021, Nghệ An dự kiến hoàn thành xây dựng 21 dự án giao thông với tổng số vốn đầu tư hơn 1.091 tỷ đồng.

Hà Tĩnh xây dựng trung tâm Logistics Khu kinh tế Vũng Áng rộng hơn 133ha

2 Giờ trước

Đây là bước quan trọng để Hà Tĩnh xây dựng, hình thành trung tâm logistics, phù hợp với xu thế phát triển.

Đà Nẵng: Hơn 15.000 tỷ đồng xây dựng thành phố môi trường

3 Giờ trước

Sáng nay (19/4/2021), Sở Tài nguyên và Môi trường (TN&MT) Đà Nẵng đã tổ chức họp báo giới thiệu Đề án “Xây dựng Đà Nẵng - Thành phố môi trường giai đoạn 2021 – 2030" và Chương trình Đại nhạc hội Thế giới nước..

Abivin - Giải pháp tối ưu hoạt động logistics

7 Giờ trước

Hơn 5 năm kể từ ngày thành lập tới nay, trải qua nhiều thăng trầm, Abivin đã tạo được nhiều dấu ấn ở thị trường logistics trong nước và quốc tế. Ông Phạm Nam Long, Giám đốc Điều hành Công ty Cổ phần Abivin Việt Nam đặt kỳ vọng, Abivin sẽ trở thành một “startup kỳ lân” trong tương lai, tạo ra nhiều giải pháp thiết thực nhằm tối ưu hóa hoạt động trong ngành dịch vụ logistics Việt Nam.

Thời tiết

Hiện tại

°

Nguồn: Weathers Underground

Tỷ giá ngoại tệ

Tỷ giá ngoại tệ cập nhật vào 19/04/2021 15:54
Mã NTTiền mặtChuyển khoảnBán
USD22,955.0022,985.0023,165.00
AUD17,408.6817,584.5318,135.81
EUR26,803.9627,074.7128,204.24
GBP31,130.9531,445.4032,431.23
JPY206.39208.47217.17
SGD16,887.0317,057.6017,592.36
THB652.53725.03752.26
Nguồn: Vietcombank

Giá xăng dầu

Giá xăng, dầu cập nhật ngày 19/04/2021 11:54
Loại xăng dầuĐơn vịGiá vùng 1Giá vùng 2
Dầu hỏa 2-KVND/L1282013070
DO 0,001S-VVND/L1449014770
DO 0,05S-IIVND/L1414014420
E5 RON 92-IIVND/L1780018150
Xăng RON 95-IIIVND/L1897019340
Xăng RON 95-IVVND/L1907019450
Nguồn: Petrolimex
Tạp chí VLR tuyển dụng Trưởng ban Phát triển kinh doanh

Tạp chí VLR tuyển dụng Trưởng ban Phát triển kinh doanh

Ngày 01/04/2021 lúc 10:43

     GIỚI THIỆU VỀ TẠP CHÍ VIETNAM LOGISTICS REVIEW-       Tên đơn vị                         : Tạp chí Vietnam Logistics Review -       Tên viết tắt                        : VLR-       Ngành nghề hoạt động      : Báo...

Abivin - Optimizing logistics operations

Abivin - Optimizing logistics operations

7 Giờ trước

After 5 years of establishment, how different has Abivin been and what difficulties has...