Trung Luong - My Thuan:

Overcoming difficulties to finish the task on schedule

(VLR) “There is no story that the investor suspended construction of Trung Luong - My Thuan Expressway”. That was the affirmation of Mr. Ho Minh Hoang, Chairman of Trung Luong - My Thuan BOT Co. before the suspension of the Management Board.

“There is no story that the investor suspended construction of Trung Luong - My Thuan Expressway”. That was the affirmation of Mr. Ho Minh Hoang, Chairman of Trung Luong - My Thuan BOT Co. before the suspension of the Management Board.

Clear up misunderstanding of material quality

The company has run a check but they did not find any violation; therefore they did not have any solutions yet. In addition, a number of papers gave out improper news, making staff in the project puzzled. The Board of Executive had requested a temporary stop for finding and clarify violations (if any) to have control on origin and quality of materials provided to the project by adjusting checking procedures.

In addition, implementation of social distancing affected the schedule. What is more, dykes for saline intrusion made material transport difficult. However, the President of the Board of Administration of Trung Luong - My Thuan Group affirmed to keep his commitment to the Prime Minister: the work will be finished by Tet of 2021 to serve people’s transport on Tet holiday and will be completely finished by the end of 2021.

Nguyen Quang Vinh, Deputy General Director of Trung Luong- My Thuan BOT Co., said until December of 2019, the People’s Committee of Tien Giang Province handled 100% land of the main route. A number of works of infrastructure, telecommunication and electricity needed to be removed will be finished in the second quarter of 2020.

Besides, although there have been negative impacts from the pandemic of COVID-19 that have affected the whole society, all staff has strictly implemented measurements against the pandemic in accordance to the guideline from the PM in the Direction no.16/CT-TTg dated March 31st, 2020. With determination of overcoming difficulties, the project has been finished over 40% (a 30% increase compared to the time of March 2019). Until April 2020, the contractors on site have been speeding up the work of treating weak ground. Wick drains have been installed at all tender package, layer reinforcement has been focused on, together with observing consolidated standards in accordance to technical instructions.

“Investors and related parties frequently check the work quality as regulated. Changing states of all the items is allowed only when the work is checked in accordance to the Project regulation,” affirmed Vinh.

Currently the investor has installed 50 monitoring cameras in all the site and have an inspection group giving daily reports in photos. The investors will install more cameras at asphalt concrete mixing stations in the coming time.

Vinh also said a 7-step checking process has been set up to check materials at mine, in transport process, at the lab and when transporting to the site. Unqualified materials will be eliminated.

As a respond for the coronavirus outbreak, a number of senior consultants in the sytem wrote a letter to suggest making a reduction of their remuneration to share difficulties with the group. However, Ho Minh Hoang- President of the Board of Administration of Deo Ca Group, President of the Board of Administration of Trung Luong - My Thuan BOT Co.- did not agree and affirmed:” Although we suffered from negative impacts from the pandemic, Deo Ca Group does not delay salary payment or make any reduction to anyone of the staff in the whole system”.

“We are making attempts to set out appropriate work solution to ensure our employees’ income, we left no one behind. We have been able to do that for our 35 years of development. The group will not make late salary payment or any reduction, financial accumulation has always been reserved for enterprise’s risks. The first priority is for employees’ payment,” Hoang said

Although there has been no particular assistance from the Government for impacts from the pandemic, Deo Ca Group has done it in its own way: In the holidays of April 30th and the Laborers’ Day of May 1st, rewarding salary will be maintained for all staff in the group.

According to Tran Van Bon- Director of the Department of Transport of Tien Giang Province, there was some information about quality of project materials. And the department worked with the Project Board of Management and the BOT company to have a check on materials in the site. At the current time, quality of the materials used in the site ensure the technical standards, especially with the item of reinforcing weak ground.

Unable to finish settlement of the budget

Currently, the owner’s capital and credit capital have been disbursed to meet the project’s schedule; the capital from the national budget has been unsettled. Particularly, VND 2,186bn of the National Budget was planned for the project, VND 1,776bn was disbursed by the People’s Committee, VND 410bn has not been disbursed.

With the capital that has not been disburse, the People’s Committee of Tien Giang Province had documents sent to the Ministry of Finance, the Ministry of Transport and the Ministry of Planning& Investment (the Documents no.5016/UBND-KTTC, no.5542/UBND-KTTC dated December 24th, 2019), and the Ministries had responding documents (the Documents no.15299/BTC-DT dated December 17th, 2019, no.272/BGTVT-KHDT dated January 9th, 2020 and no.514/BKHDT-KTDPLT dated January 22nd, 2020).

On the basis, the PM has direction (Conclusion Announcement no.93/TB-VPCP dated March 8th, 2020) asking “… the People’s Committee of Tien Giang province solves the matter of the remaining national budget. The investor is responsible for managing and using it efficiently as planned”.

On March 18th, 2020, the People’s Committee had the document no.1138/UBND-KTTC asking for guideline of using the national budget to assist the project. On March 19th, 2020, the Government Office continued to have the document no.2115/ VPCP-KTTH to the Ministry of Planning& Investment, the Ministry of Transport and the Ministry of Finance to ask for their ideas to the People’s Committee of Tien Giang Province’s request.

So, after nearly 5 months since the PM’s decision of handling capital to the project there is still VND 410bn of the National Budget that has not been disbursed. (The commitment on assisting capital from the authorized State’s organizations and the investors has not been carryout in accordance to the signed contract).

Quang Thành

Ý kiến bạn đọc

Chưa có ý kiến nào. Hãy là người để lại ý kiến đầu tiên.

Ý kiến của bạn

0

Tối thiểu 10 chữTiếng Việt có dấuKhông chứa liên kếtGửi bình luận

Vui lòng nhập mã bảo mật để gửi bình luận lên hệ thống
Gửi bình luận

Đèo cả với sứ mệnh hoàn thiện công trình thế kỷ

Ngày 05/06/2020 lúc 09:00

Đúng 15 năm trước, ngày 5/6/2005, hầm Hải Vân - hầm đường bộ lớn nhất Đông Nam Á - chính thức được đưa vào sử dụng. Ngay thời điểm đó, công trình hầm đường bộ Hải Vân đã được đánh giá mang ý nghĩa quan trọng. Tuy nhiên, để trở thành công trình tối ưu và hoàn chỉnh hơn nữa, phải mất đến 15 năm sau và sứ mệnh đó đặt lên vai Tập đoàn Đèo Cả. Đích đến đã rất gần rồi.

Bà Rịa - Vũng Tàu kích cầu du lịch: Giá dịch vụ giảm tới 50%

Ngày 06/06/2020 lúc 09:12

Hàng chục doanh nghiệp tỉnh Bà Rịa - Vũng Tàu cùng tham gia kích cầu du lịch, giảm giá dịch vụ nhưng chất lượng phục vụ không giảm.

Tái cấu trúc chuỗi cung ứng, tạo thuận lợi cho luân chuyển hàng hóa

Ngày 05/06/2020 lúc 15:42

Phát biểu tại cuộc họp báo ngay sau khi kết thúc Hội nghị Bộ trưởng Kinh tế ASEAN (AEM) và Hội nghị Bộ trưởng Kinh tế ASEAN+3 (AEM+3) trực tuyến, Bộ trưởng Trần Tuấn Anh khẳng định, các nước thống nhất mục tiêu cao nhất là tiếp tục đảm bảo phòng, chống dịch Covid-19 hiệu quả, đồng thời phối hợp chặt chẽ, đảm bảo những chương trình hợp tác về kinh tế - xã hội.

Bám sát mục tiêu, triển khai hiệu quả các Nghị quyết của Chính phủ

Ngày 05/06/2020 lúc 15:37

Trong những tháng đầu năm, dù chịu tác động của dịch bệnh Covid -19 song Bộ Công Thương đã chủ động đưa ra các chương trình, kế hoạch và giải pháp để thực hiện Nghị quyết số 01/NQ-CP của Chính phủ về những nhiệm vụ, giải pháp chủ yếu thực hiện Kế hoạch phát triển kinh tế - xã hội.

Thời tiết

TP Hồ Chí Minh

Hiện tại

33°

Mây rải rác

08/06

26° - 34°

Mưa giông vào buổi chiều

09/06

25° - 33°

Mưa giông vào buổi chiều

10/06

25° - 32°

Mưa giông

Nguồn: Weathers Underground

Tỷ giá ngoại tệ

Tỷ giá ngoại tệ cập nhật vào 07/06/2020 15:55
Mã NTTiền mặtChuyển khoảnBán
USD23,130.0023,160.0023,340.00
AUD15,868.2716,028.5616,530.95
EUR25,737.7825,997.7627,050.38
GBP28,690.7028,980.5129,888.87
JPY205.45207.53215.93
SGD16,291.2116,455.7716,971.55
THB652.67725.19752.43
Nguồn: Vietcombank

Giá xăng dầu

Giá xăng, dầu cập nhật ngày 07/06/2020 11:55
Loại xăng dầuĐơn vịGiá vùng 1Giá vùng 2
Dầu hỏa 2-KVND/L87508920
DO 0,001S-VVND/L1104011260
DO 0,05S-IIVND/L1074010950
E5 RON 92-IIVND/L1240012640
Xăng RON 95-IIIVND/L1312013380
Xăng RON 95-IVVND/L1322013480
Nguồn: Petrolimex
Cargo Transport Direct Flight Vietnam- Europe

Cargo Transport Direct Flight Vietnam- Europe

Ngày 28/05/2020 lúc 11:21

PTC-GSA, together with its aviation partners, launched a cargo direct flight from HCMC- Europe: cargo from HCMC will...