My Thuan-Can Tho expressway open in 2021:

will the gate be open?

(VLR) On March 24th, 2020, the Ministry of Transport decided to change the investor of the preparation progress of the project of My Thuan- Can Tho Expressway, Phase I.

4 years of having no decisions

On the morning of March 8th, 2020, the Prime Minister Nguyen Xuan Phuc, together with the Government’s working group, the Ministry of Transport, ministries and central sectors, in a check of the project of Trung Luong- My Thuan emphasiezed : "it is only with determination the express way to Can Tho can be completed. Together with the expressway from HCMC – Trung Luong, the whole expressway of HCMC- Trung Luong- My Thuan- Can Tho will be completed in 2021”.

Four years ago, on March 21st, the PM agreed the policy of investing in the project of My Thuan- Can Tho Expressway with the document no.463/TTg-KTN.

Until August 28th, 2017, the Ministry of Transport approved the project; on April 3rd, 2018 approve the file for preselecting biding and assigned Thang Long Administration Board to carry out. On June 29th, 2019, the result of preselecting biding was reported to the Ministry of Transport. On July 17th, 2019, the Ministry nullified the result. On October 8th, 2019, the Ministry approve the adjustment of the project. On March 24th, 2020, the Ministry had a decision to assign Cuu Long Corporation for Investment Development and Project Management of Infrastructure to be the investor for the preparation investment phase, replacing the Thang Long Project Administration Board.

March 8th, 2020, the Prime Minister Nguyen Xuan Phuc, together with the Government’s working group, the Ministry of Transport, ministries and central sectors, in a check of the project of Trung Luong- My Thuan

March 8th, 2020, the Prime Minister Nguyen Xuan Phuc, together with the Government’s working group, the Ministry of Transport, ministries and central sectors, in a check of the project of Trung Luong- My Thuan

So, 4 years after the project had been approved by the Government, the Ministry of Transport has still been in the preparation investment phase and 2 years after the project approval, the choice of investor and ground clerace work have not been carried out although there is capital from the Government’s budget allocated.

Quality of suggestion, development plans of the transport sector by the Ministry of Transport have always have a question mark hanging over. And it is not very difficult to see. For example, in the bidding of the North- South Expressway, international bidding was carried out in spite of warnings of risks from foreign enterprises; then the result was nullified and local bidding was carried out; and with obstacles from credit capital, the Ministry suggested changing to form of PPP…

If the project of My Thuan- Can Tho has no feasible solutions and having progresses as Trung Luong- My Thuan previously, there will be problems in term of precedures, time will be lenghtend and it is impossible to open in 2021 as guidance from the PM.

Will the gate be open?

Luu Xuan Thuy- the Deputy President of the Board of Administration of the Deo Ca Group- affirmed

“If we are believed and assigned to implement the project, we will apply the administrative executive model and mobilize existing equipment and staff at the site to carry out”.

Affirmed Luu Xuan Thuy- Deputy President of the Board of Administration of the Deo Ca Group.

besides having to carry out the project of Trung Luong- My Thuan Expressway on schedule: to be finished in 2020 and open in 2021, BOT Trung Luong- My Thuan JSC has summited to the PM the project of extending Trung Luong- My Thuan Expressway by adding a sector of 23km from My Thuan- Can Tho to the project. The People’s Committee of Tien Giang Province will have the rights to adust and extend the project, and the People’s Committee of Vinh Long and Dong Thap will carry out land clearance works in their own areas.

“If we are believed and assigned to implement the project, we will apply the administrative executive model and mobilize existing equipment and staff at the site to carry out, ” said Thuy.

A representative of Deo Ca Group said the capital structure of the express way section of My Thuan- Can Tho includes VND 2,400 bn from the Government’s budget and the rest from other enterprises as BOT Trung Luong-My Thuan JSC, Deo Ca Group and others partners. And Deo Ca Group together with other investors and contractors in projects of Deo Ca Tunnel, Bac Giang- Lang Son- Huu Nghi Expressway and Trung Luong- My Thuan will mobilize owners’ capital and other legal sources to meet the construction progress.

Based on calculations and particular suggestion Thuy confirmed the expressway from HCMC to Can Tho will open in 2021, and finish in 2022 to shorten the feecollecting time for the project payback from 14 years and 8 months to 12 years and 6 months (2 years and 2 months shorter). The project has had agreements from provinces the project going through as Vinh Long, Dong Thap, Can Tho. However, whether it is implemented or not depends on the governing body- the Ministry of Transport.

Quang Thành

Ý kiến bạn đọc

Chưa có ý kiến nào. Hãy là người để lại ý kiến đầu tiên.

Ý kiến của bạn

0

Tối thiểu 10 chữTiếng Việt có dấuKhông chứa liên kếtGửi bình luận

Vui lòng nhập mã bảo mật để gửi bình luận lên hệ thống
Gửi bình luận

Điểm danh các dự án giao thông lớn khởi công năm 2021

14 Giờ trước

Trong năm 2021, Bộ GTVT dự kiến khởi công xây dựng khoảng 19 dự án, công trình với tổng mức đầu tư gần 200 nghìn tỷ đồng.

Ký kết quy chế phối hợp giữa Cục Hải quan TP. HCM và Hiệp hội VLA

5 Giờ trước

Sáng ngày 28/1, Cục Hải quan TP. HCM và Hiệp hội Doanh nghiệp dịch vụ Logistics Việt Nam (VLA) đã thực hiện nghi thức ký kết Quy chế phối hợp giữa hai bên nhằm nâng cao hiệu quả hợp tác, tăng cường kết nối trong hoạt động dịch vụ logistics, cụ thể là đối với các đại lý Hải quan.

Tạp chí VLR phát hành giai phẩm Khát vọng xuân 2021

8 Giờ trước

Ngày 28/01, Tạp chí Vietnam Logistics Review (VLR) ra mắt giai phẩm Khát vọng xuân 2021. Đây là món quà ấm áp, ý nghĩa dành cho độc giả nhằm khép lại một năm Canh Tý 2020 với khá nhiều biến động và cùng nhau hướng đến một năm mới - Tân Sửu 2021 an lành, thịnh vượng, hạnh phúc cho mọi người, mọi nhà.

Doanh nghiệp ngành bán lẻ chịu tác động từ COVID-19 như thế nào?

13 Giờ trước

Dù vốn hóa ngành bán lẻ tăng 8% so với đầu năm nhưng theo SSI Research, đại dịch COVID-19 đã tác động tiêu cực lên ngành bán lẻ trong năm 2020...

Thời tiết

Hiện tại

°

Nguồn: Weathers Underground

Tỷ giá ngoại tệ

Tỷ giá ngoại tệ cập nhật vào 28/01/2021 21:52
Mã NTTiền mặtChuyển khoảnBán
USD22,940.0022,970.0023,150.00
AUD17,159.1017,332.4217,875.81
EUR27,041.4727,314.6228,454.17
GBP30,710.6131,020.8231,993.35
JPY214.46216.62225.66
SGD16,884.9217,055.4717,590.18
THB678.59753.99782.31
Nguồn: Vietcombank

Giá xăng dầu

Giá xăng, dầu cập nhật ngày 28/01/2021 11:52
Loại xăng dầuĐơn vịGiá vùng 1Giá vùng 2
Dầu hỏa 2-KVND/L1190012130
DO 0,001S-VVND/L1339013650
DO 0,05S-IIVND/L1304013300
E5 RON 92-IIVND/L1630016620
Xăng RON 95-IIIVND/L1727017610
Xăng RON 95-IVVND/L1737017710
Nguồn: Petrolimex